(PITTSBURGH, PENNSYLVANIA) Pittsburgh International Airport will open its new $1.7 billion landside terminal on Tuesday, November 18, 2025, marking the largest change to the region’s air travel experience in a generation. The long-planned facility brings check-in, ticketing, security, and baggage together in one connected building, with airport officials saying the overhaul will cut the time from car to plane by half. Travelers heading through the new space will see a single, expanded TSA checkpoint designed to handle more people with less waiting, faster baggage delivery, and simpler movement between the curb, check-in counters, and airside gates.
Checkpoint and screening improvements

The project combines years of design work and construction with an emphasis on practical improvements that matter to passengers.
- The single consolidated TSA checkpoint features 12 lanes, up from 7, with the latest screening machines and automated bin return to keep lines moving.
- The Transportation Security Administration notes that modern lanes and better bin systems help reduce bottlenecks and improve throughput.
- Federal guidance for screening is available through the TSA.
Airport leaders say these upgrades will be felt most during busy morning and evening peaks, when the checkpoint often strains under the flow of departures. They plan heavier staffing around the TSA checkpoint and customer service desks during the first weeks after opening to guide people through the new flow.
Baggage system redesign
Behind the scenes, the airport’s baggage system has been reworked to make bags arrive at carousels far more quickly.
- The redesign cuts the baggage belt network from eight miles to three miles.
- The goal is to reduce delivery times by 50%.
- Shorter belt runs mean fewer points where bags can get stuck, making the system easier to maintain and more predictable during storms and holiday surges.
For passengers landing late at night or rushing to make tight connections, the difference between a short wait and a long delay can decide whether a trip ends smoothly.
Parking, curb access, and pre-booking
Parking and curb access have been reshaped to match the new terminal flow.
- Terminal Garage with 3,300 covered spaces — twice the previous covered capacity.
- A Terminal Lot within a five-minute walk of the terminal.
- A Shuttle Lot with thousands more spaces and heated shelters for winter.
The airport says pre-booking for parking opens November 14, 2025, giving travelers a chance to reserve spots before the holiday season. These options are intended to reduce circling for parking and curbside congestion, a common source of stress for families and business travelers alike.
Skybridge and passenger experience
The physical connection between the new landside terminal and the airside gates is a signature feature.
- A three-level Skybridge creates a high, light-filled path between landside and airside.
- Designers say it evokes the moment drivers exit the Fort Pitt tunnels and see the skyline.
- Along the Skybridge, travelers will find expanded concessions, green terrace access, and a welcoming “Welcome Point” where friends and relatives can meet arriving passengers.
This is an attempt to restore the “greeter spot” many remember from older terminals while maintaining today’s security rules and passenger flow.
“The Skybridge restores a welcoming greeter spot while keeping security and flow in mind.” — Airport design intent
Roadway and operational layout
Operational changes extend beyond the terminal interior.
- The roadway network around the airport has been rebuilt, totaling 27 lane miles to separate departing and arriving traffic.
- This separation helps keep ride-hailing, shuttles, and private cars from clogging the same curb space.
- Different terminal levels now split outflows by trip purpose, improving access for families with strollers and travelers with reduced mobility.
Airport leaders say the new space and layout are built to scale with future demand without requiring a maze of add-ons.
Economic impact and local sourcing
The terminal project has had a large economic reach for the Pittsburgh region.
- Estimated $2.5 billion in economic impact over the life of the build.
- More than 14,000 jobs created.
- About 90% of the workforce and materials were sourced locally.
- 16,000 tons of locally fabricated structural steel used in construction.
Local trades, engineers, and suppliers anchored the effort, which helped keep schedules and quality tight while putting paychecks into nearby communities.
Leadership and broader aims
Airport CEO Christina Cassotis has framed the project as a reset of how the airport serves Western Pennsylvania and the broader United States 🇺🇸 travel network.
- First priority: a smoother trip through the front door — car to check-in to TSA checkpoint, then across the Skybridge to the gates.
- Secondary goals: reconnect the airport with the region’s identity and reduce wasted time for crews and carriers.
- According to analysis by VisaVerge.com, the single, streamlined entry point reflects a wider U.S. trend toward consolidation to shrink processing times and improve reliability during peak periods.
Timeline, readiness, and opening-day plans
The new terminal arrives after more than a decade of planning and several years of construction.
- Work was listed as over 94% complete in late 2025, with crews finishing interiors and testing systems.
- The opening was timed just before the Thanksgiving rush to give airlines and ground teams a short window to activate the new spaces and retire older ones.
- Ground transportation operators have been briefed on new pickup and drop-off areas, and airlines have rehearsed cutover plans for counters, bag belts, and crew routes.
If the switchover holds, airport officials expect the first passenger experience on opening day to feel seamless, with wayfinding signs and staff stationed at key junctions.
Passenger benefits and cautions
For domestic and international travelers, the consolidated approach promises:
- Fewer transfers between buildings and fewer crowding points.
- Faster security screening and more direct movement between parking, check-in, and gates.
- Better lighting, more seating, more restrooms near lines, and spaces to regroup without blocking traffic.
- Vantage points on the Skybridge for families and aviation fans alike.
Airport officials caution that the first weeks after opening may bring learning curves, so travelers should plan accordingly.
- Recommendation: arrive with the usual buffer time.
- Look for new signs pointing to the consolidated TSA checkpoint.
- Expect a shorter walk than before, but be prepared for staff guidance during the transition.
Final outlook
With larger parking capacity, better baggage systems, and a layout designed to cut time from curb to seat, Pittsburgh International Airport is betting travelers will feel the difference from their first visit.
If systems work as designed, November 18, 2025 will not just mark a ribbon-cutting, but a reset of how Pittsburgh starts and ends its journeys.
This Article in a Nutshell
Pittsburgh International Airport’s new $1.7 billion landside terminal opens November 18, 2025, consolidating check-in, TSA security, and baggage to cut car-to-plane time by half. The TSA checkpoint grows to 12 lanes, baggage belt length drops from eight to three miles to speed delivery, and parking pre-booking opens November 14 with a 3,300-space covered garage. The three-level Skybridge and rebuilt roadways improve passenger flow. Officials expect reduced wait times, better reliability, and regional economic benefits, including 14,000 jobs and $2.5 billion impact.