On July 17, 2025, a major legal decision changed the future of Brussels Airport. Belgium’s Council for Permit Disputes canceled the airport’s environmental permit, saying the Flemish government did not follow the European Union’s rules for handling aircraft noise. This update explains what happened, who is affected, what changes now, and what actions are needed for those involved with Brussels Airport. It also looks at what this means for the future, especially for people and businesses who depend on the airport or are affected by its operations.
What Changed: Annulment of Brussels Airport’s Environmental Permit

The Council for Permit Disputes, which reviews important legal complaints about permits in Flanders, decided that the environmental permit given to Brussels Airport in March 2024 was not valid. The main reason was that the Flemish government did not follow the “Balanced Approach” required by the European Union (EU) Regulation 598/2014. This rule says that before putting limits on flights or noise, governments must first try other ways to reduce noise, like using quieter planes or changing flight paths. Only if those steps do not work can they set strict limits on flights or night operations.
The canceled permit had included:
– A limit of 240,000 flights per year by 2032
– A 30% cut in night-time noise by 2030
– Tougher rules for night flights, but not a total ban
These rules were meant to protect people living near the airport from noise, but airlines and other groups said they were too strict and would hurt business.
Who Is Affected by the Decision
This decision affects many groups:
– Brussels Airport Company (BAC): The company that runs the airport now has to work under its old permit until a new one is ready.
– Airlines (like Brussels Airlines): Airlines do not face new flight or noise limits for now, but they must prepare for possible changes in the future.
– Local governments and residents: People living near the airport will not see new noise protections right away, but they can take part in the new permit process.
– Flemish government: Officials must now create a new permit that follows all EU rules and includes input from everyone involved.
– European Union: The EU will watch closely to make sure Belgium follows its noise and environmental rules.
Effective Dates and What Happens Next
- Permit Annulment: The permit was canceled on July 17, 2025.
- Airport Operations: Brussels Airport can keep running under its old permit until at least June 30, 2029 (some sources say July 8, 2029). There is no immediate change to flights or airport activities.
- Deadline for New Permit: The Flemish government must issue a new, legal permit by the 2029 deadline.
Original environmental permit issued
Permit annulled by Council for Permit Disputes
Brussels Airport can operate under old permit until this date
Some sources suggest this as the latest date for old permit
Flemish government must issue a new legal permit
Required Actions for Stakeholders
If you are involved with Brussels Airport, here’s what you need to know and do:
For Airlines and Airport Operators:
– Continue operations as usual under the old permit until 2029.
– Prepare for possible new rules in the next permit, especially regarding noise and flight numbers.
– Take part in the new consultation process to make sure your concerns are heard.
– Invest in quieter aircraft and better noise control, as these will likely be important in the new permit.
For Local Governments and Residents:
– Stay informed about the new permit process and upcoming public consultations.
– Share your views during the consultation period to help shape future noise and environmental rules.
– Monitor updates from the Flemish Environment Ministry and Brussels Airport Company.
For the Flemish Government:
– Start a new permit process that follows all EU rules, especially the “Balanced Approach.”
– Hold public and stakeholder consultations to gather input from airlines, local governments, residents, and environmental groups.
– Complete research and impact studies to support the new permit.
– Issue a new, legal permit by the 2029 deadline to avoid future legal problems.
For the European Union:
– Oversee the process to make sure Belgium follows EU law and the “Balanced Approach.”
– Provide guidance if needed to help Belgium meet its obligations.
Implications for Pending Applications and Ongoing Projects
If you have a pending application or project related to Brussels Airport, here’s what you should expect:
- No immediate changes to current operations or approvals. The airport will keep running as before until 2029.
- Future projects (like new flight routes or airport expansions) may face more review or delays as the new permit is developed.
- Noise and environmental rules could change in the new permit, so plan for possible new requirements.
- Stay in touch with authorities and check official updates to avoid surprises.
Key Legal Issue: The “Balanced Approach” Explained
The heart of this legal dispute is the “Balanced Approach,” a rule from the International Civil Aviation Organization (ICAO) and the European Union. This approach says that before governments limit flights or set strict noise rules, they must first try other ways to reduce noise. The four steps are:
- Reduce noise at the source: Use quieter planes and engines.
- Land-use planning: Make sure homes, schools, and hospitals are not built too close to airports.
- Noise abatement procedures: Change flight paths or times to reduce noise over homes.
- Operating restrictions: Only limit flights or ban night flights if nothing else works.
The Council for Permit Disputes said the Flemish government skipped some of these steps and went straight to tough restrictions. This broke EU law, so the permit was canceled.
Stakeholder Reactions and Statements
Many groups had strong opinions about the decision:
- Brussels Airlines CEO Dorothea von Boxberg welcomed the ruling. She said the airline is already investing in quieter planes, like the A320neo, and wants to work with others for fair solutions.
- Brussels Airport Company (BAC) also appealed the permit, especially the rule that forced them to pay €10 million a year to the rail company Infrabel. The court said this payment was not legal.
- Flemish Environment Minister Jo Brouns said the ruling shows the need to respect EU rules and balance business needs with protecting the environment. He promised a new, open permit process with input from everyone.
- Industry groups like Voka want a permit that supports jobs and economic growth.
- Environmental groups like Bond Beter Leefmilieu want stronger rules to protect people’s health and the environment.
- Federal mediator Philippe Touwaide criticized recent airport plans for not doing enough to protect the environment.
Historical and Broader Context
This is not the first time Brussels Airport has faced legal and political battles over noise and environmental impact. For years, there have been fights between airlines, local governments, residents, and environmental groups about how to balance the airport’s economic benefits with the need to protect people from noise and pollution.
Recent court decisions have also forced the Belgian government to change flight paths and improve how it studies the airport’s environmental impact. This makes the rules for Brussels Airport even more complicated.
Policy and Regulatory Outlook: What to Expect Next
The Flemish government has already started working on a new permit. This process will include:
– Research and impact studies to understand the effects of airport operations.
– Public and stakeholder consultations so everyone can share their views.
– Talks with airlines, local governments, and environmental groups to find fair solutions.
The new permit must follow the “Balanced Approach” and all EU rules. It must balance the needs of the economy, the environment, and public health. The Brussels Region’s appeal against the old permit was not accepted, but the Walloon Region and several towns are still involved in the process.
Practical Implications for Travelers, Workers, and Businesses
If you travel through Brussels Airport, work there, or do business with the airport, here’s what you need to know:
- No immediate changes to flights, schedules, or airport services. The airport will keep running as usual for now.
- Future changes are possible after 2029, depending on the new permit’s rules.
- Airlines may invest in quieter planes and change flight schedules to meet new noise rules.
- Jobs and business opportunities at the airport are safe for now, but future rules could affect how the airport grows.
Summary Table: Key Facts (as of July 19, 2025)
Item | Details |
---|---|
Permit Annulment Date | July 17, 2025 |
Permit Annulled By | Council for Permit Disputes (Flanders) |
Main Legal Issue | Breach of EU “Balanced Approach” (Regulation 598/2014) |
Immediate Operational Impact | None; airport operates under previous permit until July 2029 |
Flight Cap (Annulled) | 240,000 annual movements by 2032 (no longer in force) |
Night Restrictions | 30% reduction in night noise by 2030 (no longer in force) |
Financial Burden | €10 million/year Diabolo charge to Infrabel (struck down) |
Deadline for New Permit | June 30, 2029 (some sources: July 8, 2029) |
Key Stakeholders | Brussels Airlines, BAC, Flemish Gov’t, local regions, EU, residents |
Next Steps | New permit process with full EU-compliant consultation and impact study |
Official Resources and Where to Get More Information
For the latest updates and official information, you can visit:
– Brussels Airport Company (BAC)
– Flemish Environment Ministry
– Council for Permit Disputes
– European Commission Aviation Noise Policy
These sites provide news, legal documents, and updates on the permit process and airport operations.
Analysis from VisaVerge.com suggests that this legal decision is a turning point for Brussels Airport and could set an example for other airports in the European Union. The case shows how important it is for governments to follow EU rules and listen to all stakeholders when making big decisions about airports and the environment.
Actionable Takeaways and Next Steps
- If you are an airline or airport operator: Keep up with the new permit process and be ready to adjust your operations to meet future rules.
- If you are a local resident or government: Take part in public consultations and share your concerns or ideas for better noise and environmental protections.
- If you are a traveler or business: Watch for updates, but expect no immediate changes to your plans or services at Brussels Airport.
- If you are a policymaker: Make sure to follow the “Balanced Approach” and all EU rules to avoid legal problems and build trust with all groups involved.
The next few years will be important for everyone connected to Brussels Airport. The new permit process will shape how the airport grows, how it protects the environment, and how it serves travelers and businesses. By staying informed and involved, all stakeholders can help create a fair and workable solution for the future.
For more details on the European Union’s noise policy and the “Balanced Approach,” you can visit the European Commission’s official aviation noise policy page. This resource explains the rules that airports and governments must follow across the EU.
As the situation develops, keep checking official channels and news sources for the latest updates on Brussels Airport’s permit process and what it means for you.
Learn Today
Environmental Permit → Official authorization for airport operations ensuring compliance with environmental laws and noise regulations.
Balanced Approach → An EU and ICAO policy prioritizing noise reduction methods before imposing operational restrictions on airports.
Council for Permit Disputes → Belgian authority that reviews and rules on legal complaints about permits in Flanders.
Noise Abatement Procedures → Flight path or operational changes designed to reduce aircraft noise impact on nearby communities.
Diabolo Charge → A €10 million annual fee previously imposed on Brussels Airport for rail infrastructure costs, declared illegal.
This Article in a Nutshell
On July 17, 2025, Brussels Airport’s environmental permit was annulled for EU regulation violations. Operations continue until 2029, while authorities develop a new permit following the Balanced Approach, balancing economic growth with noise control to protect residents and businesses affected by the airport’s operations and future development plans.
— By VisaVerge.com